[ARCHIVED] 2025 Hickory Lane Reconstruction Project

Hickory Lane Reconstruction Project Update - Utility Delay

UPDATE 8/1:
Work on the Hickory Lane reconstruction project resumed on 7/30. Crews have commenced installation of the 48-inch underground storm sewer pipe, progressing at a rate of approximately 140 feet per day. Currently, installation is complete up to Hawthorne Drive and continuing westward. Due to the utility conflicts, the project completion date has been moved to the first week of November. Full schedule details are available by visiting the following linked document.

UPDATE 7/25:
The Village regrets to inform the public WE Energies and AT&T did not account for existing underground utilities during the project’s planning phase. As a result, the Village’s contractor was forced to vacate the site and pause all underground installation work until the conflict is resolved.
The Village is actively working with WE Energies and AT&T to expedite a resolution, allowing contractors to resume work as soon as possible.

Construction hazards remain on-site, and the road remains closed to through traffic. Travelers may, however, navigate around the construction area by utilizing Jackson Drive and/or Glen Brooke Drive between Sherman Road and Main Street. While a revised project timeline is not yet available, staff remain hopeful that construction will resume soon and that the project will still be completed by the end of October.
We appreciate your patience and understanding as we work through this unexpected disruption.

UPDATES IN MAY:

The Hickory Lane Reconstruction Project will run throughout the summer of 2025. Plan to travel different routes while roads are closed to through traffic. See the Hickory Lane Reconstruction Project Map for more information.

The Phase One - Cedar Creek to Pine Drive segment is anticipated to begin Monday, June 23rd. Materials and equipment will be moved in and staged between June 18th and June 20th. The contractor will be onsite on Monday, June 23rd, for the first full day of work.

The Phase Two - Stonehedge Drive to Cedar Creek segment will immediately follow Phase One and will be completed by mid-September.

Questions may be directed to Public Works Director Jack Straehler at 262-677-0707 or Gremmer & Associates, Inc. Project Manager Jeff Chvosta at 262-578-5800.


Facebook Twitter Email

Other News in Public Works

Mailbox Damage

Mailbox Damage?

Posted on: January 29, 2026
Snowman

24-hour Snow Removal

Posted on: December 15, 2025

Winter Parking Restriction

Posted on: December 1, 2025

2025-2026 Dog Park Project

Posted on: December 3, 2025 | Last Modified on: January 28, 2026
Construction

2026 Road Project Information

Posted on: December 3, 2025