The Hickory Lane Reconstruction Project will run throughout the summer of 2025. Plan to travel different routes while roads are closed to through traffic. See the Hickory Lane Reconstruction Project Map for more information.
Phase One - Cedar Creek to Pine Drives segment is anticipated to start the third or fourth week of June. Previously, the segment was scheduled to start May 22. The project is currently delayed due to relocation of gas services.
Phase Two - Stonehedge Drive to Cedar Creek is tentatively scheduled to run August 4 through approximately September 12.
Questions may be directed to Public Works Director Jack Straehler at 262-677-0707 or Gremmer & Associates, Inc. Project Manager Jeff Chvosta at 262-578-5800.