In 2025 the Village has contracted for maintenance of two public pedestrian paths located on the east side of Glen Brooke Drive and Jackson Drive.
- Glen Brooke Drive Path
- Segment - East side of Glen Brooke Drive, from Glen Hill Drive (offset 125 feet south) to Sherman Road.
- Scope - To remove the existing pavement, stabilize soils, regrade, and place new pavement.
- Contractor - Poblocki Paving.
- Timeline - Pavement removal will occur the week of 7/14. Stabilization and regrading of soils will occur the weeks of 7/28 and 8/4. Paving is scheduled to occur the week of 8/11.
- UPDATE on 8/21 - Paving will occur the week of 8/25
- Jackson Drive Path
- Segment - East side of Jackson Drive, from the terminus of Hickory Lane Park Path south to Sherman Road.
- Scope - Crack filling and seal coating.
- Contractor - Johnson and Sons.
- Timeline - TBD, completion on or before 10/31.
- UPDATE on 8/21 - Patching will commence the week of 8/25. Seal coating will commence the week of 9/1.
Pedestrians are asked to avoid the project work zones until after the projects have concluded. Please contact DPW Staff at 262-677-0707 if you have any further questions or concerns.